The Evolution of CDEs and Their Architectural Limits

Fig. 4. Four generations of CDEs
Documents → processes and entities → knowledge and processes → operations and asset state. The question the system answers changes from “Where is the current version?” to “Who should do what, where and when next?”
Generation 1: Document Storage
First-generation CDEs, such as Aconex, which appeared more than 20 years ago, brought order to project document management: storing and transmitting drawings and documents, legally significant correspondence, access rights and file versions. Documentation moved through these systems from the client to the designer, from the designer to the contractor, and back to the client and the asset operator.
The early versions of these systems were not designed to work with BIM models and had no mobile applications.
Generation 2: Creating and Managing Processes
Over the past decade, second-generation CDE leaders Autodesk Construction Cloud (ACC) and Procore have moved from storage to process management: routed document approvals, requests for information (RFIs) and issues, work planning, acceptance and certification of completed work, reporting, smartphone inspections, and budgets and cost changes linked to contracts. ACC gained native integration with Revit, Navisworks and AutoCAD: model collaboration, clash detection and issues linked to elements.
The key change is that the document has given way to the entity. An RFI, site instruction, NCR or acceptance certificate is described by a set of attributes: originator, recipient, BIM element, site location, priority, deadline, status, related documents and decisions made. The system begins to work with objects in the production process, rather than files.
In 2026, the second generation became agentic. In June, Procore introduced more than 150 agentic actions for creating and modifying RFIs, Submittals, Daily Logs and other objects. In September, Autodesk announced AI agents operating on project data and positioned ACC as an end-to-end AI-native AECO platform.
Generation 3: Knowledge Management
Second-generation agentic features accelerate work with documents and processes. But an architecture designed for people limits what AI can do:
The agent operates on top of documents rather than within the project model. To understand the context, it rereads the files every time. This is expensive, slow and does not scale to the entire project.
Formats are not designed for AI. Proprietary CAD formats are accessible only through APIs, while open IFC relies on cross-references between lines and was created as an exchange format, rather than a format the model can generate and edit (Section 4.2).
The process does not know the state of the asset. A workflow records that a document has been approved, but not that a structure has been constructed, accepted and paid for.
There is no execution and verification loop. The system does not assign tasks to people on site or confirm physical results.
There is no memory or context management. Project and company knowledge does not accumulate in a form convenient for the model, and every request starts from scratch.
There is no harness infrastructure. Agent permissions, context management, available tools, human confirmation, action auditing, token control and emergency shutdown are not built into the core of existing CDEs.
These limitations cannot be removed by adding another AI agent on top of an existing CDE. An architectural transition is needed: the CDE itself must become an environment optimized for collaboration between people, algorithms and LLMs—a Construction AI Harness.
Documents, BIM models, schedules and cost estimates become sources of knowledge for AI agents, rather than the final outputs of a digital process. Using that knowledge, agents will be able to generate specific operational tasks—deliver materials, carry out installation, perform an inspection, resolve an issue, accept completed work—and support the full construction cycle: brief → design solution → production task → physical operation → result verification. Eventually, robotic machinery will carry out these tasks alongside people and companies.
Generation 4: Operations Management
Finally, the next stage of CDE development is the transition from managing project knowledge and information processes to a machine-readable operational model of the project. The CDE will then evolve into a Construction Operating System (COS): a platform connecting project data with real actions, generating and initiating decisions, assigning tasks to designers, contractors and suppliers, coordinating work, and verifying and accepting the result.